- Conducted an environmental assessment of the interior and
exterior of a complex manufacturing site in New Jersey,
including soil and groundwater sampling and laboratory analysis;
and surveys for mercury, radiation, PCBs and asbestos-containing
materials. Establish criteria for and implemented pilot scale
mercury remediation project. Supervised asbestos, mercury and
soil remediation, including health and safety, and compliance
monitoring of contractors' actions and crews. Prepared progress
and compliance reports to the NJDEP.
- Conducted an environmental site assessment for a lighting
manufacturing facility in New Jersey. Scope of work included
soil and groundwater sampling and laboratory analysis; surveys
for mercury, PCBs and asbestos-containing materials; and testing
for leaking underground storage tanks. Supervised or assisted in
the preparation of specifications, selection of contractors,
supervision of remediation including tank removals, soil
cleanup, mercury removal from floor drains and sanitary sewer
lines, and asbestos removals, performed compliance sampling and
monitoring and issued reports to the NJDEP.
- Conducted the initial environmental assessment of a New
Jersey manufacturing facility and prepared the ECRA/ISRA
Sampling and Analysis Plan. Conducted sampling for
decontamination/decommissioning in areas of suspected petroleum
hydrocarbons, PCB, mercury and asbestos contamination. Prepared
remediation specifications and solicited contractor bids for
remediation of the contamination.
- Conducted an ECRA/ISRA investigation and remediation at a
New Jersey chemical manufacturing site. Prepared and implemented
the Remedial Investigation Plan, which included abatement of
asbestos-containing building materials, in-place closure and/or
removal of several underground storage tanks, and the removal of
soils contaminated with hazardous materials.
- Conducted Phase I Environmental Site Assessments at more
than thirty (30) undeveloped and developed residential and
commercial properties in New Jersey. Some of the commercial
properties have included office buildings, a real estate agency,
a lumber yard, a large butcher shop, a hardware store, a
painting contractor, a general aviation airport and several
small manufacturing facilities. Phase II activities have
included sampling for asbestos, lead-based paints, radon, and
urea formaldehyde.
- Conducted an environmental assessment of a New Jersey
facility involved in the manufacture of feather-stuffed pillows,
quilts, and mattresses. Prepared the ECRA/ISRA Initial Notice,
the Sampling and Analysis Plan, a site-specific Health and
Safety Plan, and a Remediation Plan. Sampling and laboratory
analysis included suspect asbestos-containing building
materials, soil and groundwater. Leak testing of underground
fuel storage tank. Preparation of specifications, selection of
contractors, and supervision of remedial actions, including tank
removal, soil and groundwater cleanup and asbestos removal.
- Conducted Phase I Environmental Site Investigation at a New
Jersey Airport for a banking firm. Scope of work included
sampling for radon, asbestos, lead-based paints, contaminated
soil due to surface stains and soil sampling to determine tank
integrity for ten (10) active and inactive underground storage
tanks.
- Conducted asbestos survey at a
passenger station for a New Jersey rail transportation
organization. Prepared specifications for the asbestos abatement
monitoring conducted while the station remained in full
operation.
- Conducted Phase I Environmental
Site Assessment of a New Jersey site prior to a roadway
construction project. Phase II investigative activities included
confirmatory asbestos sampling and soil sampling to delineate
contamination associated with surface stains and underground
storage tanks.
- Designed and supervised the
development of a site investigation and remediation program for
a New Jersey transportation company. Prepared Remedial
Investigation and Remedial Action Work Plan to address
environmental concerns at a rail yard. The program included
delineation of soil and groundwater contamination, and pumping
tests to obtain hydrogeologic data for design of a treatment
system. Developed an integrated strategy for recovery and
monitoring well placement and managed engineering staff in
design and installation of a groundwater treatment system. Also
worked closely with the client and NJDEP to resolve NJDEP permit
issues regarding the discharge of treated groundwater.
- Performed aquifer tests in support
of a Water Allocation Permit application to NJDEP-BWA for a New
Jersey metals refining facility. Prepared hydrogeological
report, permit application, and supporting documentation for
permit, which was approved.
- Designed and conducted a passive
soil vapor survey for a New Jersey manufacturing facility,
followed by installation of interior borings to collect soil and
groundwater samples in order to investigate potential migration
pathways and to delineate chlorinated solvent contamination of
soil and groundwater under a building.
- Supervised monitoring well
investigation to determine distribution of free product at a
former rail yard for a New Jersey transportation company.
- Performed a Preliminary
Assessment under ISRA for a former specialty chemical
manufacturing facility. Work involved site reconnaissance,
interviews with former site personnel and local officials, and
records review. Resulted in a “No Further Action” (NFA)
determination by NJDEP.
- Conducted a Phase I Environmental
Site Assessment of a New Jersey metal forming plant.
Investigation revealed significant impact below building that
had been missed by previous consultants. Subsequently conducted
extensive soil and groundwater investigation showing no
remaining source for contamination of groundwater remains.
Obtained closure of most soil AOCs. Conducting soil background
investigation that includes geophysical investigation to target
sample locations and groundwater monitoring program for the
site.
- Conducted a remedial investigation
for a former metal plating facility in New Jersey under ISRA.
Soil and groundwater had been impacted by metals and chlorinated
VOCs. Used groundwater and soil sampling results to show that
much of the metals contamination was due to historic fill, and
VOC contamination was due to offsite sources.
- Conducted site-wide investigation
under ECRA/ISRA of a former flexible packaging facility.
Responded to releases of fuel oil and toluene into nearby
surface waters. Removed two (2) large tank farms and addressed
all soil contamination to the satisfaction of the NJDEP.
Delineated groundwater contamination in fractured bedrock.
Designed, installed, and operated a large-scale groundwater pump
and treat system to address the fuel oil and toluene
contamination. Conducted step drawdown and constant rate pumping
tests on a series of recovery wells. Work also involved
hydrofracturing wells located in fractured bedrock to improve
recovery. Interpreted test data to determine effect of
fracturing on recovery. Subsequently conducted groundwater
modeling of fate and transport of contaminants to successfully
justify cessation of active remediation and to evaluate
potential migration paths for contamination potentially
migrating from offsite.
- Conducted investigation for former
owner of manufacturing facility. Previous investigation had been
mishandled by former consultant. Worked closely with the NJDEP
and new owner of site to show how extensive site redevelopment
had changed site conditions. Installation and sampling of
limited monitoring well network showed no groundwater
contamination. Provided information to the NJDEP that was able
to show adequacy of previous soil excavation, which avoided a
potentially extensive re-investigation effort. This included
extensive review of work conducted in the late 1980s and early
1990s, as well as plant records. Performance of a limited soil
excavation has resulted in NFA under ISRA.
- Prepared series of Remedial Action
Progress Reports for a former New Jersey manufacturing facility,
documenting performance of a treatment system for groundwater
contaminated by chlorinated solvents. Used groundwater modeling
and pumping test data to calculate capture zone of the recovery
system and demonstrate protection of a sensitive receptor to the
NJDEP.
- Conducted a remedial investigation
and prepared a Remedial Action Workplan for soil contaminated by
hydraulic oil for a New Jersey metal-forming facility.
Investigation involved the installation of trenches and borings
inside an operating facility, which was completed without
disrupting operations. Project also included recommendations for
prevention of further oil contamination via application of an
advanced coating to a machine sump in floor.